The quick test

If any part of the scaffold stands on, overhangs or blocks a road, pavement or verge that the public can use, you need a scaffold licence from the council that looks after that road. That's section 169 of the Highways Act 1980. It applies to a single tower on the pavement outside a terraced house just as much as to a big commercial job.

If the scaffold stands entirely on private land, such as a driveway, a garden or a fenced site, and nothing reaches over the pavement, you don't need a highway licence. You may still need the landowner's permission, and the work itself may need other approvals.

Things that catch people out

  • Overhangs count. A scaffold built on a front garden that leans out over the pavement, or a fan or gantry over it, still needs a licence.
  • Verges and the bit in front of the wall count. The highway often runs right up to the front wall of the property, not just the paved part.
  • Hoardings need a licence too (section 172), and so do skips, and some councils' licences cover barriers and pedestrian walkways around the scaffold.
  • Short jobs aren't exempt. A scaffold up for two days on the pavement needs a licence as much as one up for two months.

Who applies

Usually the scaffolding firm, because the licence covers the scaffold and the firm holds the insurance the council asks for. Some councils let the householder or main contractor apply. Whoever applies is responsible for keeping to the licence conditions.

What the council asks for

  • The site address and the dates the scaffold goes up and comes down.
  • A sketch or plan showing where it stands and how much pavement or road it takes.
  • How pedestrians will get past safely, and lighting and signs at night.
  • Proof of public liability insurance. Of the 104 councils that state a minimum, 74 ask for £5 million and 28 ask for £10 million.
  • The fee, and enough notice before the start date.

Where to apply

To the highway authority for the road, which in two-tier areas is the county council, not the district (see which council to apply to). Councils take applications through their own websites, a portal, email or GOV.UK.

Type the site's postcode and Chaseable shows the right council, its fee, its notice period and a link to where you apply. Then read what licences cost and how much notice to give.