Scaffold licence notice periods and apply-by dates

How much notice councils want, how to work out the last day to apply, and the difference between notice and processing time.

Figures from each council's own pages, checked up to 27 Nov 2026.

Notice period, apply-by date and processing time

  • Notice period: how far ahead of the scaffold going up the council wants your application. A council asking for 14 days' notice wants the application at least 14 days before the start date.
  • Apply-by date: the last day you can apply and still meet the notice period. It's the start date minus the notice period.
  • Processing time: how long the council says it takes to deal with an application. Some councils publish this instead of a notice period. It works the same way in practice: apply at least that long before you need the licence.

Working out the apply-by date

Say the scaffold goes up on 7 December and the council wants 14 days' notice. Count back 14 days: the application has to be in by 23 November. Apply on the 24th and the council can refuse to issue the licence in time, or charge an urgent fee if it offers one.

Watch for working days. Ten working days is two full weeks, not ten calendar days, and bank holidays don't count. Chaseable converts working days to calendar days for you, so the dates it shows are real calendar dates.

How much notice councils want

88 of England's 153 highway authorities publish a notice period. The most common is 14 days (35 councils). Here's how they split:

Published notice periods
Notice periodCouncils
14 days35
7 days20
5 days10
3 days4
28 days4
10 days3
11 days3
21 days3
4 days2
1 day1
6 days1
12 days1
15 days1

The councils wanting the most notice

Leave the most time for these. A late application here can delay a job by weeks.

Published processing times

Where a council gives a processing time rather than a notice period, the most common answers are 14 days (19 councils), 7 days (16 councils), 4 days (4 councils).

When a council publishes neither

36 councils state neither a notice period nor a processing time. For those, allow at least two weeks and ring the council if the job is urgent. Chaseable says clearly when a council doesn't publish a figure rather than guessing one.

Never miss an apply-by date

Look up the site's postcode and add the day the scaffold goes up: Chaseable shows the apply-by date for that council. Save it as a permit with a free account and you'll get an email a week before, two days before, the day before and on the day, plus a text the day before and on the day.