Council to apply to
Medway Council
Checked by handApply at least
7 days
before the scaffold goes upLicence fee£82
Notice7 days
Council takesNot published by this council: processing time
Fee covers: Application fee of £82, plus £90 licence and site inspection fee on approval, plus £90 monthly licence and site inspection fee for each month the licence is needed.
See all 3 prices
| Application fee | £82 |
|---|---|
| Licence and site inspection fee | £90 |
| Monthly licence and site inspection fee | £90 |
Extension(A monthly licence and site inspection fee of £90 for each month you need the licence. If you need it for longer than one month you must apply for an extension; the council emails 5 days before expiry to ask.)£90
- Insurance needed
- £5 million public liability
What the council asks for (7)
- Provide details about your company
- Upload a copy of your public liability insurance certificate showing expiry date and cover amount (minimum £5 million)
- Provide details about the scaffolding or hoarding, including size, location and dates in place
- Pay the non-refundable application fee
- Apply at least 5 working days before scaffolding or hoarding is erected
- Apply for a licence extension if needed for longer than one month
- Check one.network website to ensure no roadworks or public events clash with requested dates
In the council's words
“a fee of £82 at time of application a licence and site inspection fee of £90 on application approval a monthly licence and site inspection fee of £90 for each month you need the licence”
medway.gov.ukChecked 13 Oct 2026