Council to apply to
Gloucestershire County Council
Checked by handApply at least
12 days
before the scaffold goes upLicence fee£145
Notice12 days
Council takes8 days
Fee covers: Scaffolding/Hoarding Licence - Minimum period 28 Days Charge
Extension(Extension Period: 7 days Charge: £36 per 7 days)£36
Other charges
- Urgent/Retrospective FeeNon-refundable fee for urgent or retrospective applications£62.50
- Licence PenaltyPenalty for scaffolding/hoarding licence non-compliance£1,050
- Additional site visit feeCharged per additional site visit£120
- Amendment Form FeeFee to change scheduled dates on an amendment form£30
- Insurance needed
- £5 million public liability
What the council asks for (5)
- Submit application at least 12 calendar days before work starts
- Traffic management plan required for scaffolding/hoarding licence
- Provide all required documentation to avoid delay
- Amendments can only be made within 5 calendar days of licence start
- Renewal licence must be applied for if exceeding time period with 8+ days notice
In the council's words
“Minimum period: 28 Days Charge: £145”