7 days
before the scaffold goes upLicence fee£85
Notice7 days
Council takes7 days
Fee covers: Non-refundable £50 admin fee plus tiered licence fee based on duration and domestic/commercial use; e.g. domestic up to 7 days £85, commercial up to 7 days £128 (see full table for other durations).
See all 22 prices (1 to 720 days)
| Domestic - Up to 7 days | £85 |
|---|---|
| Domestic - Between 7 days to 1 month | £156 |
| Domestic - Between 1 to 3 months | £382 |
| Domestic - Between 3 to 6 months | £693 |
| Domestic - Between 6 to 9 months | £1,004 |
| Domestic - Between 9 to 12 months | £1,314 |
| Domestic - Between 12 to 15 months | £1,625 |
| Domestic - Between 15 to 18 months | £1,949 |
| Domestic - Between 18 to 21 months | £2,247 |
| Domestic - Between 21 to 24 months | £2,558 |
| Commercial - Up to 7 days | £128 |
| Commercial - Between 7 days to 1 month | £255 |
| Commercial - Between 1 to 3 months | £679 |
| Commercial - Between 3 to 6 months | £1,272 |
| Commercial - Between 6 to 9 months | £1,880 |
| Commercial - Between 9 to 12 months | £2,473 |
| Commercial - Between 12 to 15 months | £3,080 |
| Commercial - Between 15 to 18 months | £3,674 |
| Commercial - Between 18 to 21 months | £4,291 |
| Commercial - Between 21 to 24 months | £4,975 |
| Container/welfare unit/mobile crane licence | £212 |
| Mobile platform permit | £185 |
ExtensionNot published by this council: extension fee
Other charges
- Administration feeNon-refundable administration fee for each application£50
- Insurance needed
- £5 million public liability
- Longest licence
- 720 days
What the council asks for (11)
- Application must be completed by the contractor undertaking the work.
- Check if the road is adopted or unadopted; unadopted roads need landowner permission.
- Provide copy of public liability insurance (not less than £5 million, valid for full licence period).
- Provide a site drawing showing position of structures/obstructions in the road.
- Provide planning application number, where planning permission is required.
- Provide the dimensions of each structure.
- Provide traffic management plan details.
- Scaffolding/hoarding wrapping multiple streets requires a licence for each street.
- Multiple structures (e.g. containers) on site each require separate licences.
- Licence permit must be clearly displayed on the structure at all times.
- No works can take place until approval has been received.