Council to apply to
London Borough of Bexley
Checked by handApply by
Not published
This council doesn't say how much notice it needs. Allow at least two weeks and check with them.
Licence fee£150up to 3 months
NoticeNot published by this council: notice period
Council takesNot published by this council: processing time
Fee covers: Scaffold/Hoarding Licence fee for up to 3 month period (plus Highway Protection Licence £589, total £739)
See all 3 prices (90 to 90 days)
| Licence fee | £150 |
|---|---|
| Highway Protection Licence | £589 |
| Total | £739 |
Extension(Additional payment of £150 per month required to extend a licence beyond the initial 3-month period)£150
Other charges
- Refundable depositDeposit based on square meterage used, refundable if no damage caused to highway
- Lamp/safety call-out chargeCharge if council's contractors are called out to lamp the scaffold/hoarding or make it safe
- Longest licence
- 90 days
What the council asks for (12)
- Meet on-site with an officer to discuss placement and take measurements before approval
- Minimum headroom of 2.1 metres maintained for pedestrians
- Overhead protection must be provided against falling objects
- Supports must not be placed on any manhole or access cover
- No part of scaffold within 450mm of the kerb line
- Temporary pedestrian ways never less than 1 metre wide
- Guard and sign approaches if temporary footway is in the carriageway
- Rigid pedestrian barriers with hand and tapping rails, kerb ramps where needed
- Vertical members painted white up to eye level
- Lamps required at 3-metre centres at night/poor visibility
- Adequate insurance cover required for injury or damage claims
- Construction Certificate and liability insurance certificate displayed on site before work starts
In the council's words
“Licence fee £150 Highway Protection Licence £589 Total £739 for a 3 month period”